TIME AND WORK MCQs
Time & Work, Work And Wages
Total Questions : 1512
| Page 148 of 152 pages
Answer: Option D. -> 1800
NUMBER OF BOTTLES PRODUCED BY 1 MACHINE IN A MINUTE
= 270/6 NUMBER OF BOTTLES PRODUCED BY 10 MACHINES IN 4 MINUTES
= (270/6)*10*4 = 1800
NUMBER OF BOTTLES PRODUCED BY 1 MACHINE IN A MINUTE
= 270/6 NUMBER OF BOTTLES PRODUCED BY 10 MACHINES IN 4 MINUTES
= (270/6)*10*4 = 1800
Answer: Option A. -> 7
WORK DONE BY 10 MEN IN 1 DAY = 1/7
WORK DONE BY 1 MAN IN 1 DAY = (1/7)/10 = 1/70
WORK DONE BY 10 WOMEN IN 1 DAY = 1/14
WORK DONE BY 1 WOMAN IN 1 DAY = 1/140
WORK DONE BY 5 MEN AND 10 WOMEN IN 1 DAY = 5 × (1/70) + 10 × (1/140)
= 5/70 + 10/140 = 1/7
=> 5 MEN AND 10 WOMEN CAN COMPLETE THE WORK IN 7 DAYS
WORK DONE BY 10 MEN IN 1 DAY = 1/7
WORK DONE BY 1 MAN IN 1 DAY = (1/7)/10 = 1/70
WORK DONE BY 10 WOMEN IN 1 DAY = 1/14
WORK DONE BY 1 WOMAN IN 1 DAY = 1/140
WORK DONE BY 5 MEN AND 10 WOMEN IN 1 DAY = 5 × (1/70) + 10 × (1/140)
= 5/70 + 10/140 = 1/7
=> 5 MEN AND 10 WOMEN CAN COMPLETE THE WORK IN 7 DAYS
Answer: Option B. -> 5,760 litres
NO EXPLANATION IS AVAILABLE FOR THIS QUESTION!
NO EXPLANATION IS AVAILABLE FOR THIS QUESTION!
Answer: Option B. -> 30 days
NO EXPLANATION IS AVAILABLE FOR THIS QUESTION!
NO EXPLANATION IS AVAILABLE FOR THIS QUESTION!
Answer: Option C. -> 4:3
PART OF WORK COMPLETED BY A MAN IN A DAY = 1/(12*20)
= 1/240 PART OF WORK COMPLETED BY A WOMAN IN A DAY = 1/(20*16) = 1/320 RATIO OF THEIR CAPACITIES
= (1/240):(1/320) = 320:240 = 4:3
PART OF WORK COMPLETED BY A MAN IN A DAY = 1/(12*20)
= 1/240 PART OF WORK COMPLETED BY A WOMAN IN A DAY = 1/(20*16) = 1/320 RATIO OF THEIR CAPACITIES
= (1/240):(1/320) = 320:240 = 4:3
Answer: Option A. -> 2
M1*D1*W2 = M2*D2*W1
10*3*10*32 = 30*D*8*20
D = 2 DAYS
M1*D1*W2 = M2*D2*W1
10*3*10*32 = 30*D*8*20
D = 2 DAYS
Answer: Option B. -> 9.6
PART OF WORK COMPLETED BY A AND B IN 4 DAYS
= 4*((1/16) + (1/12))
= 7/12 C CAN COMPLETE 5/12TH OF THE WORK IN 4 DAYS C CAN COMPLETE THE WHOLE JOB IN
4÷(5/12) = 9.6 DAYS
PART OF WORK COMPLETED BY A AND B IN 4 DAYS
= 4*((1/16) + (1/12))
= 7/12 C CAN COMPLETE 5/12TH OF THE WORK IN 4 DAYS C CAN COMPLETE THE WHOLE JOB IN
4÷(5/12) = 9.6 DAYS
Answer: Option B. -> 4:3
WORK DONE BY 20 WOMEN IN 1 DAY = 1/16
WORK DONE BY 1 WOMAN IN 1 DAY = 1/(16×20)
WORK DONE BY 16 MEN IN 1 DAY = 1/15
WORK DONE BY 1 MAN IN 1 DAY = 1/(15×16)
RATIO OF THE CAPACITY OF A MAN AND WOMAN =1/(15×16) : 1/(16×20) = 1/15 : 1/20
= 1/3 :1/4 = 4:3
WORK DONE BY 20 WOMEN IN 1 DAY = 1/16
WORK DONE BY 1 WOMAN IN 1 DAY = 1/(16×20)
WORK DONE BY 16 MEN IN 1 DAY = 1/15
WORK DONE BY 1 MAN IN 1 DAY = 1/(15×16)
RATIO OF THE CAPACITY OF A MAN AND WOMAN =1/(15×16) : 1/(16×20) = 1/15 : 1/20
= 1/3 :1/4 = 4:3
Answer: Option B. -> 3 3⁄7
WORK DONE BY P IN 1 DAY = 1/24
WORK DONE BY Q IN 1 DAY = 1/6
WORK DONE BY R IN 1 DAY = 1/12
WORK DONE BY P,Q AND R IN 1 DAY = 1/24 + 1/6 + 1/12 = 7/24
=> WORKING TOGETHER, THEY WILL COMPLETE THE WORK IN 24/7 DAYS = 3 3⁄7 DAYS
WORK DONE BY P IN 1 DAY = 1/24
WORK DONE BY Q IN 1 DAY = 1/6
WORK DONE BY R IN 1 DAY = 1/12
WORK DONE BY P,Q AND R IN 1 DAY = 1/24 + 1/6 + 1/12 = 7/24
=> WORKING TOGETHER, THEY WILL COMPLETE THE WORK IN 24/7 DAYS = 3 3⁄7 DAYS
Answer: Option C. -> 4 min
NO EXPLANATION IS AVAILABLE FOR THIS QUESTION!
NO EXPLANATION IS AVAILABLE FOR THIS QUESTION!