Question
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
Answer: Option C
Was this answer helpful ?
Whole work is done by A in \( \left(20\times\frac{5}{4}\right)\) = 25 days.
Now, \( \left(1-\frac{5}{4}\right)\) i.e., \(\frac{1}{5}\) work is done by A and B in 3 days.
Whole work will be done by A and B in (3 x 5) = 15 days.
A's 1 day's work = \(\frac{1}{25}\) , (A + B)'s 1 day's work = \(\frac{1}{15}\)
So, B's 1 day's work = \( \left(\frac{1}{15}-\frac{1}{25}\right)=\frac{4}{150}=\frac{2}{75}\)
So, B alone would do the work in \( \frac{75}{2}.\) = \( 37^{\frac{1}{2}}\) days.
Was this answer helpful ?
Submit Solution