Question 71. .  Frequency distribution curves
  1.    having a single lump, are called uninodal curves
  2.    if symmetrical, are called normal curves
  3.    if not symmetrical, are called skew curves
  4.    all the above.
 Discuss Question
Answer: Option D. -> all the above.
Question 72. .  Pick up the PERT event from the following :
  1.    Digging of foundation started
  2.    Digging of foundation completed
  3.    Laying of concrete started
  4.    All the above.
 Discuss Question
Answer: Option D. -> All the above.
Question 73. . Pick up the correct statement from the following :
  1.    Optimistic time estimate refers to activities
  2.    Pessimistic time estimate refers to activities
  3.    Most likely time estimate refers to activities
  4.    All the above.
 Discuss Question
Answer: Option D. -> All the above.
Question 74. .  Pick up the correct statement from the following :
  1.    Earliest expected time is denoted by TE
  2.    Latest occurrence time is denoted by 71
  3.    Contractual obligation time is denoted by I's
  4.    All the above.
 Discuss Question
Answer: Option D. -> All the above.
Question 75. . Pick up the correct statement from the following :
  1.    Forward pass is used for calculating earliest expected time
  2.    Backward pass is used for calculating the latest occurence time
  3.    Maximum value of earliest expected time is used if there are more than one value of any event
  4.    All the above.
 Discuss Question
Answer: Option D. -> All the above.
Question 76. . Pick up the correct statement from the following :
  1.    The difference of latest occurence time and earliest expected time, is called slack
  2.    The activities connecting the events having zero slack, lie on the critical path
  3.    The critical path consumes the maximum time
  4.    All the above.
 Discuss Question
Answer: Option D. -> All the above.
Question 77. .  In CPM analysis,
  1.    emphasis is given to activities
  2.    uncertainties are not allowed
  3.    activities are represented by arrows
  4.    all the above.
 Discuss Question
Answer: Option D. -> all the above.
Question 78. . Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
  1.    Earliest occurrence time of the event from which the activity arrow originates, is called earliest start time of the activity
  2.    Earliest occurrence time of the event from which the activity arrow originates plus the duration of the activity, is called earliest finish time of the activity
  3.    The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
  4.    All the above.
 Discuss Question
Answer: Option D. -> All the above.
Question 79. . Consider the following statements regarding the critical path of a project network 1. 1. A path is a set of nodes connected by arrows which begin at its initial node of the network and end at the terminal 2. The length of a path in a network is the total time it takes to travel the path 3. The shortest path in a project network is called critical path 4. Activities on the critical path are called critical activities Of these statements:
  1.    1, 2 and 3 are correct
  2.    2, 3 and 4 are correct
  3.    1,3 and 4 are correct
  4.    1, 2 and 4 are correct
 Discuss Question
Answer: Option C. -> 1,3 and 4 are correct
Question 80. . Consider the following statements regarding Early start and early finish times 1. The earliest possible that the job can begin, is called the early start of the job 2. The early finish of a job is early start time plus the job's completion time 3. For jobs with no predecessors, the early start is equal to start time of the project 4. The early start of a job is the largest of the early finish times of all of the immediately predecessors. Of these statements:
  1.    1 is correct
  2.    1 and 2 are correct
  3.    1, 2 and 3 are correct
  4.    1, 2, 3 and 4 are correct
 Discuss Question
Answer: Option B. -> 1 and 2 are correct