Question 61. . Critical Path Net Work helps an engineer
  1.    to concentrate his attention on critical activities
  2.    to divert the resources from non-critical advanced activities to critical activities
  3.    to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
  4.    all the above.
 Discuss Question
Answer: Option D. -> all the above.
Question 62. . The time which results in the least possible construction cost of an activity, is known
  1.    normal time
  2.    slow time
  3.    crash time
  4.    standard time.
 Discuss Question
Answer: Option B. -> slow time
Question 63. .  Pick up the correct statement from the following :
  1.    The float may be positive, zero or negative
  2.    If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
  3.    If the float of an activity is negative, delay in its performance is bound to delay the completion of project
  4.    All the above.
 Discuss Question
Answer: Option D. -> All the above.
Question 64. .  A critical ratio scheduling
  1.    establishes the relative priorities among various activities on a common basis
  2.    determines the status of each activity
  3.    adjusts automatically changes in activity progress
  4.    none of these.
 Discuss Question
Answer: Option D. -> none of these.
Question 65. . Pick up the incorrect statement from the following :
  1.    The activity is the time consuming part of a project
  2.    The beginning and end of a job, are called events
  3.    The activity which consumes maximum time, is called a node
  4.    Logically and sequentially connected activities and events form a network
 Discuss Question
Answer: Option C. -> The activity which consumes maximum time, is called a node
Question 66. .  A CPM family includes
  1.    CPA (Critical Path Analysis)
  2.    CPP (Critical Path Plotted)
  3.    MCE (Minimum Cost Expenditure)
  4.    All the above.
 Discuss Question
Answer: Option D. -> All the above.
Question 67. .  If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
  1.    a + m + b
  2.    a + 2rn + b
  3.    a + 4m + b
  4.    a + 5m +
 Discuss Question
Answer: Option C. -> a + 4m + b
Question 68. .  CPM is
  1.    synthesising in concepts
  2.    is built of activities oriented programme
  3.    is based on time estimate
  4.    all the above.
 Discuss Question
Answer: Option D. -> all the above.
Question 69. .  PERT is
  1.    an analytic in concept
  2.    limited of event oriented diagrams
  3.    used for research and development projects
  4.    all the above.
 Discuss Question
Answer: Option D. -> all the above.
Question 70. .  Pick up the correct statement from the following :
  1.    CPM analysis is activity oriented
  2.    PERT analysis is event oriented
  3.    CPM does not make any allowance for the uncertainties in the duration of time
  4.    All the above.
 Discuss Question
Answer: Option D. -> All the above.