Total Questions : 95 | Page 4 of 10 pages
Question 31. . Pick up the incorrect statement from the following :
  1.    The various functions under each activity, are shown by one bar on Bar Charts
  2.    Bar chart establishes the interdependency of one event on another
  3.    Only approximate percentage of the completed work is reported
  4.    None of these.
 Discuss Question
Answer: Option B. -> Bar chart establishes the interdependency of one event on another
Question 32. .  For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
  1.    1
  2.    (6)2
  3.    3
  4.    4
 Discuss Question
Answer: Option A. -> 1
Question 33. .  Mile Stone charts were invented in the year of
  1.    1910
  2.    1920
  3.    1930
  4.    1940
 Discuss Question
Answer: Option C. -> 1930
Question 34. .  Bar charts are suitable for
  1.    minor works
  2.    major works
  3.    large projects
  4.    all the above.
 Discuss Question
Answer: Option A. -> minor works
Question 35. . The first method invented for planning projects, was
  1.    Bar chart method
  2.    Milestone chart
  3.    Critical path method (CPM)
  4.    Programme Evaluation and Review Technique (PERT)
 Discuss Question
Answer: Option A. -> Bar chart method
Question 36. . Pick up the correct statement from the following :
  1.    Programme Evaluation and Review Technique, is event oriented
  2.    Programme Evaluation and Review Technique is not event oriented
  3.    Critical Path Method is event oriented
  4.    Ci-itical Path method is event oriented.
 Discuss Question
Answer: Option A. -> Programme Evaluation and Review Technique, is event oriented
Question 37. . While scheduling a project by C.P.M.
  1.    a project is divided into various activities
  2.    required time for each activity is established
  3.    sequence of various activities is made according to their importance
  4.    All the above.
 Discuss Question
Answer: Option D. -> All the above.
Question 38. . PERT analysis is based on
  1.    optimistic time
  2.    pessimistic time
  3.    most likely time
  4.    all the above.
 Discuss Question
Answer: Option D. -> all the above.
Question 39. . Critical path method
  1.    is an improvement upon bar chart method
  2.    provides a realistic approach to daily problems
  3.    avoids delays which are very common in bar charts
  4.    All the above.
 Discuss Question
Answer: Option D. -> All the above.
Question 40. . The performance of a specific task in CPM, is known
  1.    Dummy
  2.    Event
  3.    Activity
  4.    Contract.
 Discuss Question
Answer: Option C. -> Activity