Question 91. . Pick up the correct statement from the following :
  1.    A path is a set of nodes connected by arrows which begin at the initial node of the network and end at the terminal node
  2.    A path is called a critical path if it is the longest path in a project network
  3.    All the activities on the critical path are called critical activities
  4.    All tha above.
 Discuss Question
Answer: Option D. -> All tha above.
Question 92. . Pick up the correct statement from the following :
  1.    The early start time of an activity is the maximum of the early finish times of all its immediate predecessors
  2.    The sequence of the activities on the longest path in the network, is the project's critical path
  3.    The procedure of finding the early start and early finish times of each of the begining activities, then those of their successors, their successors' successors, and so on is called the forward pass through the network
  4.    All the above
 Discuss Question
Answer: Option D. -> All the above
Question 93. . Pick up the correct statement from the following :
  1.    Total slack is the difference between its late start and early start times
  2.    Total slack is the difference between its late finish and early finish times
  3.    The activities on the critical path have zero total slack
  4.    All the above.
 Discuss Question
Answer: Option D. -> All the above.
Question 94. . Pick up the correct statement from the following :
  1.    The early start time of an activity is the maximum of the early finish times of all its immediate predecessors
  2.    The sequence of the activities on the longest path in the network, is the project's critical path
  3.    The procedure of finding the early start and early finish times of each of the begining activities, then those of their successors, their successors' successors, and so on is called the forward pass through the network
  4.    All the above
 Discuss Question
Answer: Option D. -> All the above
Question 95. 0. Pick up the correct statement from the following :
  1.    Total slack is the difference between its late start and early start times
  2.    Total slack is the difference between its late finish and early finish times
  3.    The activities on the critical path have zero total slack
  4.    All the above.
 Discuss Question
Answer: Option D. -> All the above.