MCQs

Total Questions : 95 | Page 6 of 10 pages
Question 51. . The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
  1.    duration
  2.    total flat
  3.    free float
  4.    interfering float.
 Discuss Question
Answer: Option C. -> free float
Question 52. . Which one of the following represents an activity
  1.    excavation for foundation
  2.    curing of concrete
  3.    setting of question paper
  4.    all the above.
 Discuss Question
Answer: Option D. -> all the above.
Question 53. . For completion of a project, the critical path of the network represents
  1.    minimum time
  2.    maximum time
  3.    maximum cost
  4.    minimum cost.
 Discuss Question
Answer: Option A. -> minimum time
Question 54. .  In a certain project an activity C can only be started when activities A and B have been completed, which have no bearing on each other and can be started independently. The correct network for the activities, is
  1.    Activities A and B can be started independently
  2.    Activity C can be started only on completion of activity A
  3.    Activity D can be started only on completion of activity
  4.    all the above
 Discuss Question
Answer: Option D. -> all the above
Question 55. . Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following :
  1.    1. Pouring of Concrete,2. Erection of form work,3. Curing of concrete,4. Removal of form work
  2.    1. Erection of form work ,2. Pouring of concrete3. Curing of concrete,4. Removal of form work
  3.    1. Removal of form work 2. Erection of form work3. Pouring of concrete,4. Curing of concrete
  4.    1. Pouring of concrete2. Curing of concrete 3. Erection of form work 4. Removal of form work.
 Discuss Question
Answer: Option B. -> 1. Erection of form work ,2. Pouring of concrete3. Curing of concrete,4. Removal of form work
Question 56. . Which one of the following represents an event ?
  1.    concrete cured
  2.    fixing of door
  3.    plastering of walls
  4.    selecting sites
 Discuss Question
Answer: Option A. -> concrete cured
Question 57. . If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
  1.    started 5 days later
  2.    completed 5 days later
  3.    performed at slower rate in 15 days
  4.    all the above.
 Discuss Question
Answer: Option D. -> all the above.
Question 58. . In a project logic, four activities M, N, 0 and P are to be completed before starting activity Q. If the finish times of M, N, 0 and P are 12-00 hr, 14-00 hr, 15-00 hr. and 17-00 hr. respectively, the earliest event occurrence time for the activity
  1.    1200 hr.
  2.    1400 hr.
  3.    1500 hr.
  4.    1700 hr.
 Discuss Question
Answer: Option D. -> 1700 hr.
Question 59. . Critical path lies along the activities having total float
  1.    positive
  2.    negative
  3.    zero
  4.    same.
 Discuss Question
Answer: Option C. -> zero
Question 60. . The technique for establishing and maintaining priorities among the various jobs of a project, is known
  1.    Event flow scheduling technique
  2.    Critical ratio scheduling
  3.    Slotting technique for scheduling
  4.    Short interval scheduling.
 Discuss Question
Answer: Option D. -> Short interval scheduling.