Question 181. Standard time is defined as
  1.    Normal time + allowances
  2.    Normal time + idle time + allowances
  3.    Normal time + idle time
  4.    Only normal time for an operation
 Discuss Question
Answer: Option A. -> Normal time + allowances
Question 182. In a PERT chart
  1.    All activities should be numbered
  2.    Only important activities should be numbered
  3.    Only critical activities are numbered
  4.    Only selected activities are numbered
 Discuss Question
Answer: Option A. -> All activities should be numbered
Question 183. Slack of various events on the critical path in PERT/CPM chart
  1.    Increases continuously
  2.    Decreases continuously
  3.    Remain constant
  4.    May increase or decrease depending on various factors
 Discuss Question
Answer: Option C. -> Remain constant
Question 184. In process layout
  1.    Handling and backtracking of materials is too much
  2.    Production control is more difficult and costly
  3.    Routing and scheduling is more difficult
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above
Question 185. In product layout
  1.    Specialized and strict supervision is required
  2.    Machines can not be used to their maximum capacity
  3.    Manufacturing cost rises with a fall in the volume of production
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above
Question 186. A low unit cost can be obtained by following
  1.    Product layout
  2.    Functional layout
  3.    Automatic material handling equipment
  4.    Specialization of operation
 Discuss Question
Answer: Option A. -> Product layout
Question 187. Gantt chart gives information about
  1.    Scheduling and routing
  2.    Sales
  3.    Production schedule
  4.    Machine utilization
 Discuss Question
Answer: Option C. -> Production schedule
Question 188. Gantt charts provide information about
  1.    Break-even point analysis
  2.    Production schedule
  3.    Material handling layout
  4.    Determining selling price
 Discuss Question
Answer: Option B. -> Production schedule
Question 189. Scheduling gives information about
  1.    When work should start and how much work should be completed during a certain period
  2.    When work should complete
  3.    That how idle time can be minimized
  4.    Proper utilization of machines
 Discuss Question
Answer: Option A. -> When work should start and how much work should be completed during a certain period
Question 190. In PERT analysis, critical path is obtained by joining events having
  1.    +ve slack
  2.    -ve slack
  3.    Zero slack
  4.    Dummy activities
 Discuss Question
Answer: Option C. -> Zero slack