Question 161. Routing
  1.    Prescribes the sequence of operations to be followed
  2.    Determines the programme for the operations
  3.    Is concerned with starting of processes
  4.    Regulates the progress of job through various processes
 Discuss Question
Answer: Option A. -> Prescribes the sequence of operations to be followed
Question 162. PERT is applied for
  1.    Marketing programmes and advertising programmes
  2.    Installation of machinery
  3.    Research and development of products
  4.    All of these
 Discuss Question
Answer: Option D. -> All of these
Question 163. Discrepancies of bar chart techniques are
  1.    Consequential effects of lack in one activity on the finish date
  2.    Free time available for an activity can't be predicted
  3.    Effective monitoring/controlling can't be done
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above
Question 164. In Halsey 50-50 plan, output standards are established
  1.    By time study
  2.    From previous production records
  3.    From one's judgment
  4.    All of the above
 Discuss Question
Answer: Option B. -> From previous production records
Question 165. Queuing theory is associated with
  1.    Sales
  2.    Inspection time
  3.    Waiting time
  4.    Production time
 Discuss Question
Answer: Option C. -> Waiting time
Question 166. Break-even analysis can be used for
  1.    Short run analysis
  2.    Long run analysis
  3.    Average of above two run analysis
  4.    There is no such criterion
 Discuss Question
Answer: Option A. -> Short run analysis
Question 167. Work study is mainly aimed at
  1.    Determining the most efficient method of performing a job
  2.    Establishing the minimum time of completion of a job
  3.    Developing the standard method and standard time of a job
  4.    Economizing the motions involved on the part of the worker while performing a job
 Discuss Question
Answer: Option A. -> Determining the most efficient method of performing a job
Question 168. A company spends considerable amount on publicity to promote sales. This expenditure in break even chart is shown below the
  1.    Fixed cost line
  2.    Variable cost line
  3.    Total cost line
  4.    Sales revenue line
 Discuss Question
Answer: Option B. -> Variable cost line
Question 169. Positive slack on a PERT indicates that project is
  1.    Ahead of schedule
  2.    Beyond schedule
  3.    As per schedule
  4.    On critical path
 Discuss Question
Answer: Option A. -> Ahead of schedule
Question 170. Break-even point is the point where
  1.    Fixed and variable cost lines intersect
  2.    Fixed and total cost lines intersect
  3.    Variable and total cost lines intersect
  4.    Sales revenue and total expensive lines intersect
 Discuss Question
Answer: Option D. -> Sales revenue and total expensive lines intersect