Question 171. Scheduling
  1.    Prescribes the sequence of operations to be followed
  2.    Determines the programme for the operations
  3.    Is concerned with starting of processes
  4.    Regulates the progress of job through various processes
 Discuss Question
Answer: Option B. -> Determines the programme for the operations
Question 172. Which of the following plans motivates supervisors by paying a premium on time saved by workers?
  1.    Halsey plan
  2.    Rowan plan
  3.    Haynes plan
  4.    Emerson's plan
 Discuss Question
Answer: Option C. -> Haynes plan
Question 173. 'Value' for value engineering and analysis purposes is defined as
  1.    Purchase value
  2.    Saleable value
  3.    Depreciated value
  4.    Function/cost
 Discuss Question
Answer: Option D. -> Function/cost
Question 174. Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.
  1.    One-fourth
  2.    One-half
  3.    Equal to
  4.    Twice
 Discuss Question
Answer: Option B. -> One-half
Question 175. Critical Path Net Work helps an engineer
  1.    To concentrate his attention on critical activities
  2.    To divert the resources from noncritical advanced activities to critical activities
  3.    To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above
Question 176. Queueing theory is used for
  1.    Inventory problems
  2.    Traffic congestion studies
  3.    Job-shop scheduling
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above
Question 177. A critical activity has
  1.    Maximum slack
  2.    Minimum slack
  3.    Zero slack
  4.    Average slack
 Discuss Question
Answer: Option C. -> Zero slack
Question 178. Percent idle time for men or machines is found by
  1.    Work sampling
  2.    Time study
  3.    Method study
  4.    Work study
 Discuss Question
Answer: Option A. -> Work sampling
Question 179. The critical activity has
  1.    Maximum float
  2.    Minimum float
  3.    Zero float
  4.    Average float
 Discuss Question
Answer: Option C. -> Zero float
Question 180. In order that linear programming techniques provide valid results
  1.    Relations between factors must be linear (positive)
  2.    Relations between factors must be linear (negative)
  3.    Either (A) or (B)
  4.    Only one factor should change at a time, others remaining constant
 Discuss Question
Answer: Option C. -> Either (A) or (B)