Question 1471. 3. Emergency rush order can be pushed more effectively in
  1.    Job production
  2.    Automatic production
  3.    Continuous production
  4.    Intermittent production
 Discuss Question
Answer: Option D. -> Intermittent production
Question 1472. 5. The performance of a specific task in CPM is known as
  1.    Dtmuny
  2.    Event
  3.    Activity
  4.    Contract
 Discuss Question
Answer: Option C. -> Activity
Question 1473. 2. The time of completing a project in net*ork analysis is given by following time of the critical activity meeting at the final node
  1.    Early finish
  2.    Early start
  3.    Late start
  4.    Late finish
 Discuss Question
Answer: Option A. -> Early finish
Question 1474. 4. Routing assists engineers in deciding in advance
  1.    The flow of material in the plant
  2.    The methods of proper utilization of manpower
  3.    The methods of proper utilization of - machines
  4.    The layout of factory facilities
 Discuss Question
Answer: Option C. -> The methods of proper utilization of - machines
Question 1475. 1. Pick up the correct step used for scheduling a project by C.P.M.
  1.    A project is divided into various activities
  2.    Activities and the events all of the above.
  3.    Sequence of various activities is made according to their importance
  4.    Network is drawn by connecting the
 Discuss Question
Answer: Option B. -> Activities and the events all of the above.
Question 1476. 6. The artiflical acavity; which indicates that an activity following it cannot be started unle.ssfthe preceding activity is complete, is known as
  1.    Event
  2.    Dummy.
  3.    Artificial
  4.    Constraint
 Discuss Question
Answer: Option B. -> Dummy.
Question 1477. 7. A dummy activity
  1.    Is artificially introduced
  2.    Is represented by a dotted line
  3.    Does not require any time
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above
Question 1478. 8. The difference between the time available to do the job and the time required to do the job, is known as
  1.    Event
  2.    Float
  3.    Duration
  4.    Constraint
 Discuss Question
Answer: Option B. -> Float
Question 1479. 9. The probability distribution of activity times in PERT follows following distribution
  1.    Normal
  2.    Binomial
  3.    Beta
  4.    Exponential
 Discuss Question
Answer: Option C. -> Beta
Question 1480. 2. The critical activity has
  1.    Maximum float
  2.    Minimum float
  3.    Zero float,
  4.    Average float
 Discuss Question
Answer: Option C. -> Zero float,