Question 1451. 3. Slack represents the difference between the
  1.    Latest allowable time and the normal expected time
  2.    Latest allowable time and the earliest expected time
  3.    Proposed allowable time and the earliest expected time
  4.    Normal allowable time and the latest expected time
 Discuss Question
Answer: Option B. -> Latest allowable time and the earliest expected time
Question 1452. 5. A big advantage of PERT over Gant charts is that in the former case
  1.    Activities and events are clearly shown
  2.    Inter-relationship among activities is clearly shown.
  3.    Activity times are clear
  4.    Critical path can be easily determined
 Discuss Question
Answer: Option B. -> Inter-relationship among activities is clearly shown.
Question 1453. 4. PERT and CPM are
  1.    Techniques to determine project status
  2.    Aids to the decision maker.
  3.    Charts which increai-e aesthetic appearance of rooms
  4.    Aids to determine cost haplications of project
 Discuss Question
Answer: Option B. -> Aids to the decision maker.
Question 1454. 2. Which of the following depreciation sys - tern ensures that the interest be charged on the cost of machine asset every year on the book value, but the rate of depreciation every year remains constant
  1.    Sinking fund method
  2.    Straight line method
  3.    A-B-C charging method
  4.    Annuity charging method
 Discuss Question
Answer: Option D. -> Annuity charging method
Question 1455. 1. String diagram is used
  1.    For checking the relative values of various layouts
  2.    When a group of workers are working at a place
  3.    Where processes require the operator to be moved from one place to another
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above
Question 1456. 6. CPM is the
  1.    Time oriented technique
  2.    Event oriented technique
  3.    Activity oriented technique
  4.    Target oriented technique
 Discuss Question
Answer: Option C. -> Activity oriented technique
Question 1457. 7. PMTP (predetermined motion time systems) include
  1.    MTM (method time measurement)
  2.    WFS (work factor systems)
  3.    BNTS (basic motion time study)
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above
Question 1458. 8. Work study comprises following main techniques
  1.    Method study and work measurement
  2.    Method study and time study
  3.    Tithe study and work measurement
  4.    Method study and job evaluation
 Discuss Question
Answer: Option A. -> Method study and work measurement
Question 1459. 2. Queing theory is used for
  1.    Inventory problems
  2.    Traffic congestion studies
  3.    Job-shop scheduling
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above
Question 1460. 9. PERT is the
  1.    Time oriented technique
  2.    Event oriented techniqne
  3.    Activity oriented technique
  4.    Target oriented technique
 Discuss Question
Answer: Option B. -> Event oriented techniqne