2. The critical activity has
Options:
A
.
 Maximum float
B
.
 Minimum float
C
.
 Zero float,
D
.
 Average float
Answer: Option C
Submit Your Solution Below and Earn Points !
0 Likes
Next Question
Report Problem
Share
Submit Solution
Your email address will not be published.
Required fields are marked
*
More Questions on This Topic :
Question 1.
1. If TL is the largest allowable event occurrence time, total activity slack (s) is equal to....
Question 2.
0. The probability distribution of project completion in PERT follows following distribution....
Question 3.
3. The time by which the activity completion-time can be delayed without affeFting the start of succeeding activiti....without affeFting the start of succeeding activities, is lown as
Question 4.
5. Critical path moves along the activities having total float of....
Question 5.
4. Pick up the correct statement from the following....
Question 6.
8. The technique for establishing and maintaining priorities fltong the various jobs of any project is known as....
Question 7.
9. Pick up the incorrect statement from the following. A critical ratio scheduling....
Question 8.
7. The time which results in the least possible direct cost of an activity is known as ....
Question 9.
6. Critical Path Net Work helps an engineer....
Question 10.
0. PERT is....
Latest Videos
Chapter 1 - GLOBAL STEEL SCENARIO & INDIAN STEEL INDUSTRY
Part 1 : (13-04-2024)
INDUSTRY AND COMPANY AWARENESS (ICA)
Direction Sense Test
Part 1
Reasoning (Hindi)
Chapter 1 - RMHP / OHP / OB & BP
Part 1 : (14-02-2024)
GPOE
Cube & Cuboid
Part 1
Reasoning (Hindi)
Data Interpretation (DI)
Basic Concept
Reasoning (Hindi)
Counting Figures Part 1
Counting Of Straight Lines
Reasoning (Hindi)
Sail E0 free webinar
Webinars
Real Numbers
Part 7
Class 10 Maths
Real Numbers
Part 1
Class 10 Maths
Polynomials
Part 1
Class 10 Maths
Latest Test Papers
GPOE / GPA Combined 1
Free CBT Mock Test
SAIL E0 2024
Pie Chart - Test Paper 1
Data Interpretation
Reasoning & DI
Chapter 1.1 : INTRODUCTION
Chapter 1 : Raw Material Handling Plant
SAIL E0 - GPOE/GPA 2024
Chapter 3.1 : INTRODUCTION
Chapter 3 : Sinter Plant
SAIL E0 - GPOE/GPA 2024
Chapter 2.3 : COAL HANDLING PLANT - Set 1
Chapter 2 : Coke Ovens and Coal Chemicals
SAIL E0 - GPOE/GPA 2024
One click Login
Login With Google
Old way of Login
Login With Email
Submit Problem
Problem Type (Required)
Choose Problem Type
Incorrect Topic
Incomplete Question
Wrong Question
Wrong Solution
Wrong Option
Explaination : Please write a little about the issue
Submit Solution