Pick up the incorrect statement from the following:
Options:
A .  The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity
B .  The difference between the maximum time available for the job and actual time it consumes, is called total float
C .  The difference between the latest start time and earliest start time of an activity, is called total float
D .  None of these
Answer: Option D