Sail E0 Webinar
Question
Select the incorrect statement.
Options:
A .  A critical path always begins at the very first event.
B .  A critical path always terminates at the last event.
C .  Critical activities control the project duration.
D .  Critical activity is the one for which free float is zero.
Answer: Option D

Submit Your Solution Below and Earn Points !