Pick up the correct statement from the following:
Options:
A .  The float may be positive, zero or negative
B .  If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
C .  If the float of an activity is negative, delay in its performance is bound to delay the completion of project
D .  All the above
Answer: Option D