Select the incorrect statement.
Options:
A .  Earliest start of an activity is the early event time of the node it leaves
B .  Latest finish of an activity is the late event time of the node it enters
C .  Latest start of an activity is its latest finish minus its duration
D .  None of the above
Answer: Option D