Question
A and B together take 6 days to complete a task. B and C together take 12 days to complete the same task. A and C together take 8 days to complete it. If A, B and C are working together, how long does it take for them to complete the task?
Answer: Option C
(1/A)+(1/B) = (1/6) (1/B)+(1/C) = (1/12) (1/A)+(1/C) = (1/8) SOLVING THE THREE EQUATIONS,
(1/A)+(1/B)+(1/C) = (3/16) TOGETHER THEY TAKE 16/3 = 5(1/3) DAYS TO COMPLETE THE TASK.
Was this answer helpful ?
(1/A)+(1/B) = (1/6) (1/B)+(1/C) = (1/12) (1/A)+(1/C) = (1/8) SOLVING THE THREE EQUATIONS,
(1/A)+(1/B)+(1/C) = (3/16) TOGETHER THEY TAKE 16/3 = 5(1/3) DAYS TO COMPLETE THE TASK.
Was this answer helpful ?
Submit Solution