If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be
Options:
A .  2.3% and 84.1%
B .  97.7% and 84.1%
C .  97.7 % and 15.9%
D .  15.9% and 97.7%
Answer: Option A