Sail E0 Webinar
Question

A can do a work in 15 days and B in 20 days . If they work on it together for 4 days , then the fraction of the work

that is left is :


Options:
A .  `1/4`
B .  `1/10`
C .  `7/15`
D .  `8/15`
Answer: Option D

A's 1 days work  = `1/15`; B's 1 days work =  `1/20`

(A + B)'s 1 day's work = `(1/15 + 1/20) =  7/60`

(A + B)'s 4 day's work = `(7/60 xx 4) = 7/15`

`:.`      Remaining work = `(1 - 7/15) = 8/15`





Was this answer helpful ?
Next Question

Submit Solution