Question 81. The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode
  1.    Early finish
  2.    Early start
  3.    Late start
  4.    Late finish
 Discuss Question
Answer: Option A. -> Early finish
Question 82. Standard time is equal to
  1.    (Normal time) - (allowances)
  2.    (Normal time) + (allowances)
  3.    Representative time multiplied by rating factor
  4.    Normal time taken by an operation
 Discuss Question
Answer: Option B. -> (Normal time) + (allowances)
Question 83. Which of the following incentive plans ensures a part of the swing to the worker and rest to the employer?
  1.    Emerson efficiency plan
  2.    Taylor plan
  3.    Halsey premium plan
  4.    Gilbert plan
 Discuss Question
Answer: Option C. -> Halsey premium plan
Question 84. Routing is essential in the following type of industry
  1.    Assembly industry
  2.    Process industry
  3.    Job order industry
  4.    Mass production industry
 Discuss Question
Answer: Option A. -> Assembly industry
Question 85. In manufacturing management, the term 'Dispatching' is used to describe
  1.    Dispatch of sales order
  2.    Dispatch of factory mail
  3.    Dispatch of finished product of the user
  4.    Dispatch of work orders through shop floor
 Discuss Question
Answer: Option D. -> Dispatch of work orders through shop floor
Question 86. Queueing theory deals with problems of
  1.    Material handling
  2.    Reducing the waiting time or idle time
  3.    Better utilization of man services
  4.    Effective use of machines
 Discuss Question
Answer: Option B. -> Reducing the waiting time or idle time
Question 87. Work study is done with the help of
  1.    Process chart
  2.    Material handling
  3.    Stop watch
  4.    All of the above
 Discuss Question
Answer: Option C. -> Stop watch
Question 88. For handling materials during manufacture of cement, a _________ is widely used.
  1.    Belt conveyor
  2.    Bucket conveyor
  3.    Fork lift truck
  4.    Overhead crane
 Discuss Question
Answer: Option B. -> Bucket conveyor
Question 89. Frederick W. Taylor introduced a system of working known as
  1.    Line organisation
  2.    Line and staff organisation
  3.    Functional organisation
  4.    Effective organisation
 Discuss Question
Answer: Option C. -> Functional organisation
Question 90. A dummy activity
  1.    Is artificially introduced
  2.    Is represented by a dotted line
  3.    Does not require any time
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above