Question 61. The plinth area of a building not includes
  1.    Area of the walls at the floor level
  2.    Internal shaft for sanitary installations up to 2 sq m. in area
  3.    Lift and wall including landing
  4.    Area of cantilevered porch
 Discuss Question
Answer: Option D. -> Area of cantilevered porch
Question 62. In the mid-section formula
  1.    The mean depth is the average of depths of two consecutive sections
  2.    The area of mid-sections is calculated by using mean depth
  3.    The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above
Question 63. The cross-sectional area of the embankment of a canal fully in embankment in the given figure is
  1.    ½ (b₁ + b₂) h
  2.    (b₁ + b₂) h + sb²
  3.    (b₁ + b₂) + 2sh²
  4.    2 [(b₁ + b₂) (b + sh²)]
 Discuss Question
Answer: Option C. -> (b₁ + b₂) + 2sh²
Question 64. The inspection pit or chamber is a manhole provided in a base drainage system
  1.    At every change of direction
  2.    At every change of gradient
  3.    At every 30 m intervals
  4.    All the above
 Discuss Question
Answer: Option D. -> All the above
Question 65. Anti-siphonage pipe is connected to
  1.    Main soil pipe
  2.    Bottom of P trap W.C.
  3.    Top of P trap W.C.
  4.    Side of water closet
 Discuss Question
Answer: Option C. -> Top of P trap W.C.
Question 66. The 'centre line method' is specially adopted for estimating
  1.    Circular buildings
  2.    Hexagonal buildings
  3.    Octagonal buildings
  4.    All the above
 Discuss Question
Answer: Option D. -> All the above
Question 67. In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and
  1.    Breadth of the wall
  2.    Half breadth of wall on each side
  3.    One fourth breadth of wall on each side
  4.    None of these
 Discuss Question
Answer: Option B. -> Half breadth of wall on each side
Question 68. According to ISI method of measurement, the order of the sequence is
  1.    Length, breadth, height
  2.    Breadth, length, height
  3.    Height, length, breadth
  4.    None of these
 Discuss Question
Answer: Option A. -> Length, breadth, height
Question 69. The rate of an item of work depends on
  1.    Specifications of works
  2.    Specifications of materials
  3.    Proportion of mortar
  4.    All the above
 Discuss Question
Answer: Option D. -> All the above
Question 70. The cross-sections for a highway is taken at
  1.    Right angle to the centre line
  2.    30 meters apart
  3.    Intermediate points having abrupt change in gradient
  4.    All the above
 Discuss Question
Answer: Option D. -> All the above