Question 51. Carpet area does not include the area of
  1.    The walls along with doors and other openings
  2.    Bath room and lavatory
  3.    Kitchen and pantry
  4.    None of the above
 Discuss Question
Answer: Option D. -> None of the above
Question 52. While estimating the qualities for the construction of a building, the correct metric unit is
  1.    Meter for length
  2.    Cubic metre for area
  3.    Square meters for volume
  4.    Liter for capacity
 Discuss Question
Answer: Option D. -> Liter for capacity
Question 53. The area is measured correct to the nearest
  1.    0.01 sqm
  2.    0.02 sqm
  3.    0.03 sqm
  4.    0.04 sqm
 Discuss Question
Answer: Option A. -> 0.01 sqm
Question 54. The volume is measured correct to the nearest
  1.    0.01 cum
  2.    0.02 cum
  3.    0.03 cum
  4.    0.04 cum
 Discuss Question
Answer: Option A. -> 0.01 cum
Question 55. While preparing a detailed estimate
  1.    Dimension should be measured correct to 0.01 m
  2.    Area should be measured correct to 0.01 sqm
  3.    Volume should be measured correct to 0.01 cum
  4.    All the above
 Discuss Question
Answer: Option D. -> All the above
Question 56. The plinth area of a building not includes
  1.    Area of the walls at the floor level
  2.    Internal shaft for sanitary installations up to 2 sq m. in area
  3.    Lift and wall including landing
  4.    Area of cantilevered porch
 Discuss Question
Answer: Option D. -> Area of cantilevered porch
Question 57. In the mid-section formula
  1.    The mean depth is the average of depths of two consecutive sections
  2.    The area of mid-sections is calculated by using mean depth
  3.    The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above
Question 58. The inspection pit or chamber is a manhole provided in a base drainage system
  1.    At every change of direction
  2.    At every change of gradient
  3.    At every 30 m intervals
  4.    All the above
 Discuss Question
Answer: Option D. -> All the above
Question 59. Anti-siphonage pipe is connected to
  1.    Main soil pipe
  2.    Bottom of P trap W.C.
  3.    Top of P trap W.C.
  4.    Side of water closet
 Discuss Question
Answer: Option C. -> Top of P trap W.C.
Question 60. The cross-sectional area of the embankment of a canal fully in embankment in the given figure is
  1.    ½ (b₁ + b₂) h
  2.    (b₁ + b₂) h + sb²
  3.    (b₁ + b₂) + 2sh²
  4.    2 [(b₁ + b₂) (b + sh²)]
 Discuss Question
Answer: Option C. -> (b₁ + b₂) + 2sh²