Question 11. The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is
  1.    ⅓ × (b - rd)²/(r - s)
  2.    ⅓ × (b - rd)²/(r + s)
  3.    ½ × (b + rd)²/(r - s)
  4.    ⅓ × (b - rd)²/(s - r)
 Discuss Question
Answer: Option A. -> ⅓ × (b - rd)²/(r - s)
Question 12. Brick walls are measured in sq. m if the thickness of the wall is
  1.    10 cm
  2.    15 cm
  3.    20 cm
  4.    None of these
 Discuss Question
Answer: Option A. -> 10 cm
Question 13. Pick up the item whose weight is added to the weight of respective item, is
  1.    Cleats
  2.    Brackets
  3.    Bolts
  4.    All the above
 Discuss Question
Answer: Option D. -> All the above
Question 14. The item of steel work which is measured in sq.m, is
  1.    Collapsible gates
  2.    Rolling shutters
  3.    Ventilators and glazing
  4.    All the above
 Discuss Question
Answer: Option D. -> All the above
Question 15. The item of the brick structure measured in sq.m, is
  1.    Reinforced brick work
  2.    Broken glass coping
  3.    Brick edging
  4.    Brick work in arches
 Discuss Question
Answer: Option B. -> Broken glass coping
Question 16. The following item of earth work is not measured separately.
  1.    Setting out of works
  2.    Site clearance
  3.    Steps in deep excavation
  4.    All the above
 Discuss Question
Answer: Option D. -> All the above
Question 17. The trap which is provided to disconnect the house drain from the street sewer is called
  1.    Master trap
  2.    Intercepting trap
  3.    Interception manhole
  4.    All the above
 Discuss Question
Answer: Option D. -> All the above
Question 18. Pick up the excavation where measurements are made in square meters for payment.
  1.    Ordinary cuttings up to 1 m
  2.    Surface dressing up to 15 cm depths
  3.    Surface excavation up to 30 cm depths
  4.    Both (B) and (C)
 Discuss Question
Answer: Option D. -> Both (B) and (C)
Question 19. A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved.
  1.    26,000 m³
  2.    26,500 m³
  3.    27,000 m³
  4.    27,500 m³
 Discuss Question
Answer: Option D. -> 27,500 m³
Question 20. The floor area includes the area of the balcony up to
  1.    100 %
  2.    75 %
  3.    50 %
  4.    25 %
 Discuss Question
Answer: Option C. -> 50 %