Question 31. The rate of payment is made for 100 cu m (per % cu m) in case of
  1.    Earth work in excavation
  2.    Rock cutting
  3.    Excavation in trenches for foundation
  4.    All the above
 Discuss Question
Answer: Option D. -> All the above
Question 32. Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds
  1.    2.0 %
  2.    2.5 %
  3.    4.0 %
  4.    5.0 %
 Discuss Question
Answer: Option D. -> 5.0 %
Question 33. The value of 'C' of Indian type W.C. shown in the given figure is:
  1.    400 mm
  2.    450 mm
  3.    500 mm
  4.    550 mm
 Discuss Question
Answer: Option C. -> 500 mm
Question 34. The value of 'B' of Indian type W.C. shown in the given figure is:
  1.    45 cm
  2.    50 cm
  3.    30 cm
  4.    25 cm
 Discuss Question
Answer: Option A. -> 45 cm
Question 35. The value of 'A' of Indian type W.C. shown in the given figure is:
  1.    25 cm
  2.    30 cm
  3.    40 cm
  4.    45 cm
 Discuss Question
Answer: Option B. -> 30 cm
Question 36. The area of the cross-section of a road fully in banking shown in the given figure, is
  1.    [sb² + r² (2bd + sd)²]/(r² - s²)
  2.    [sb² + r² (2bd + sd)²]/(r² - s²)
  3.    [sb² + r² (2bd + sd)²]/(r - s)
  4.    None of these
 Discuss Question
Answer: Option B. -> [sb² + r² (2bd + sd)²]/(r² - s²)
Question 37. A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is
  1.    500 m3
  2.    1000 m3
  3.    1500 m3
  4.    2000 m3
 Discuss Question
Answer: Option D. -> 2000 m3
Question 38. The concrete work for the following part of the building of specified thickness is measured in square meters
  1.    Root slabs
  2.    Floors
  3.    Wall panels
  4.    All the above
 Discuss Question
Answer: Option D. -> All the above
Question 39. The expected out turn of cement concrete 1 : 2 : 4 per mason per day is
  1.    1.5 m³
  2.    2.5 m³
  3.    3.5 m³
  4.    5.0 m³
 Discuss Question
Answer: Option D. -> 5.0 m³
Question 40. The expected out turn of half brick partition wall per mason per day is
  1.    1.5 m2
  2.    2.0 m2
  3.    4.0 m2
  4.    5.0 m2
 Discuss Question
Answer: Option D. -> 5.0 m2