Question 21. Provision of sufficient freeboard eliminates _______________
i. Over-topping failure
ii. Erosion of U/s face
iii. Erosion of D/s face
iv. Cracking due to frost action
v. Gully formation
Which of the following is/are correct?
  1.    i and v
  2.    ii and iii
  3.    iv and v
  4.    i and iv
 Discuss Question
Answer: Option D. -> i and iv
Answer: (d).i and iv
Question 22. Sloughing is the process of _________________
  1.    progressive erosion
  2.    subsequent removal of soil grains from within the dam
  3.    uncontrolled seepage through the dam body
  4.    progressive removal of soil from the D/s face
 Discuss Question
Answer: Option D. -> progressive removal of soil from the D/s face
Answer: (d).progressive removal of soil from the D/s face
Question 23. The collection and removal of water before it acquires high downward velocities is ensured by provision of ____________________
  1.    berms
  2.    freeboard
  3.    burrow pits
  4.    spoil banks
 Discuss Question
Answer: Option A. -> berms
Answer: (a).berms
Question 24. In order to prevent the possibility of the cross-flow towards the earthen embankments, it is necessary to provide _____________________
  1.    counter berms
  2.    sides walls of sufficient height and length
  3.    spoil banks
  4.    sufficient freeboard
 Discuss Question
Answer: Option B. -> sides walls of sufficient height and length
Answer: (b).sides walls of sufficient height and length
Question 25. In foundation slide failure___________________________
  1.    top of embankment gets cracked and lower slope moves outward forming large mud waves near the heel
  2.    top of embankment gets cracked and lower slope moves inward forming large mud waves near the heel
  3.    bottom of embankment gets cracked and lower slope moves outward forming large mud waves near the heel
  4.    bottom of embankment gets cracked and lower slope moves inward forming large mud waves near the heel
 Discuss Question
Answer: Option A. -> top of embankment gets cracked and lower slope moves outward forming large mud waves near the heel
Answer: (a).top of embankment gets cracked and lower slope moves outward forming large mud waves near the heel
Question 26. The only provision among the following which can help control the seepage through the body of an earthen dam and thus to keep the phreatic line well within the dam width is _________________
  1.    upstream impervious cut-off
  2.    drain trench along the downstream toe
  3.    relief wells
  4.    chimney drain
 Discuss Question
Answer: Option D. -> chimney drain
Answer: (d).chimney drain
Question 27. What is provided in the form of a transition zone between the homogenous embankments-fill and rock toe?
  1.    Toe filter
  2.    Horizontal blanket
  3.    Chimney drain
  4.    Trenches
 Discuss Question
Answer: Option A. -> Toe filter
Answer: (a).Toe filter
Question 28. The length of horizontal blanket should be equal to _________________
  1.    3 times the height of the dam
  2.    4 times the height of the dam
  3.    5 times the height of the dam
  4.    6 times the height of the dam
 Discuss Question
Answer: Option A. -> 3 times the height of the dam
Answer: (a).3 times the height of the dam
Question 29. ____________________ is provided when large scale stratification occurs.
  1.    Chimney drain
  2.    Cut-off
  3.    Relief wells
  4.    Trenches
 Discuss Question
Answer: Option A. -> Chimney drain
Answer: (a).Chimney drain
Question 30. During the maintenance of an earthen dam, the apparent seepage through the foundation of the dam is best taken care of by providing ______________________
  1.    chimney drain
  2.    rock toe
  3.    drain trench along the downstream toe
  4.    upstream impervious cut-off
 Discuss Question
Answer: Option C. -> drain trench along the downstream toe
Answer: (c).drain trench along the downstream toe