Question 11. Which of the following zone in Zoned type embankment prevents piping through cracks?
  1.    Central core
  2.    Transition zone
  3.    Outer zone
  4.    Core wall
 Discuss Question
Answer: Option B. -> Transition zone
Answer: (b).Transition zone
Question 12. Which of the following earth dam is suitable only on impervious foundation?
  1.    Zoned embankment type
  2.    Homogenous embankment type
  3.    Non-homogenous type
  4.    Diaphragm type
 Discuss Question
Answer: Option B. -> Homogenous embankment type
Answer: (b).Homogenous embankment type
Question 13. The foundation pressure used in the pressure grouting is equal to _________________
  1.    2.0 D N/cm²
  2.    2.5 D N/cm²
  3.    5.0 D N/cm²
  4.    3.0 D N/cm²
 Discuss Question
Answer: Option B. -> 2.5 D N/cm²
Answer: (b).2.5 D N/cm²
Question 14. Which of the following joints justifies the two-dimensional analysis of gravity dams?
  1.    Longitudinal joints
  2.    Transverse joints
  3.    Construction joints
  4.    Contraction joints
 Discuss Question
Answer: Option B. -> Transverse joints
Answer: (b).Transverse joints
Question 15. Which of the following soil material is most preferred for the central core material of zoned embankment type dam?
  1.    Highly impervious clay
  2.    Sands or silty clays
  3.    Coarse sands
  4.    Gravels
 Discuss Question
Answer: Option B. -> Sands or silty clays
Answer: (b).Sands or silty clays
Question 16. Which embankment has the thickness of the diaphragm at an elevation less than 10 meters or the height of the embankment above the corresponding elevation?
  1.    Diaphragm type dam
  2.    Zoned type dam
  3.    Non-homogenous earth dam
  4.    Homogenous earth dam
 Discuss Question
Answer: Option A. -> Diaphragm type dam
Answer: (a).Diaphragm type dam
Question 17. During the construction of an earthen dam by hydraulic fill method, development of pore pressure becomes important in the __________________
  1.    central impervious core
  2.    pervious outer shell
  3.    transition zone
  4.    both central core and outer shell
 Discuss Question
Answer: Option A. -> central impervious core
Answer: (a).central impervious core
Question 18. The process of laying and compacting earth in layers by power rollers under OMC for construction of earthen dams is known as ______________________
  1.    Rolled fill method
  2.    Hydraulic fill method
  3.    OMC method
  4.    Compaction
 Discuss Question
Answer: Option A. -> Rolled fill method
Answer: (a).Rolled fill method
Question 19. Which of the following statement is correct with reference to earthen dams?
  1.    These dams are very costly as compared to other types
  2.    Gravity dams are less susceptible to failure as compared to rigid dams
  3.    These dams are suitable for construction on almost every type of foundation
  4.    Highly skilled labor is generally not required
 Discuss Question
Answer: Option C. -> These dams are suitable for construction on almost every type of foundation
Answer: (c).These dams are suitable for construction on almost every type of foundation
Question 20. The blanket in earth dam is provided ___________________
  1.    at the ground level on u/s side
  2.    at the ground level on the d/s side
  3.    at the ground level of the D/s side of the dam
  4.    on the D/s slope
 Discuss Question
Answer: Option A. -> at the ground level on u/s side
Answer: (a).at the ground level on u/s side