Question 21. What is used to categorize risks, assumptions, and environments so that all risk management groups can access work done on risk management?
  1.    List of Indexes
  2.    List of categories
  3.    List of keywords
  4.    both b and c
 Discuss Question
Answer: Option D. -> both b and c
Answer: (d).both b and c
Question 22. Organizing projects by product involves establishing each product project as
  1.    Centralized Element
  2.    Autonomy
  3.    Multiple element
  4.    Decentralized Element
 Discuss Question
Answer: Option A. -> Centralized Element
Answer: (a).Centralized Element
Question 23. A pure project organization overlaid on the functional divisions of the parent firm, is known as
  1.    Mixed Organizational System
  2.    Pure Project Organization
  3.    The Matrix Organization
  4.    Virtual Organization
 Discuss Question
Answer: Option C. -> The Matrix Organization
Answer: (c).The Matrix Organization
Question 24. Apart from the value of a fine design, the economic value of the time saved is immense. The value can be derived from
  1.    1 source
  2.    2 sources
  3.    3 sources
  4.    4 sources
 Discuss Question
Answer: Option B. -> 2 sources
Answer: (b).2 sources
Question 25. Choosing an organizational project structure can be determined by
  1.    Project Complexity
  2.    Step by step procedure
  3.    Nature of project
  4.    Buildup of project
 Discuss Question
Answer: Option C. -> Nature of project
Answer: (c).Nature of project
Question 26. The term that can show critical information flow, the need for concurrent tasks, is known as
  1.    Functional Design Structure
  2.    Design Matrix Structure
  3.    Design Flow Structure
  4.    Design Pattern Structure
 Discuss Question
Answer: Option B. -> Design Matrix Structure
Answer: (b).Design Matrix Structure
Question 27. If choice of project structure exists, the first task to achieve is
  1.    Identify Project plan
  2.    Identify Project Strategy
  3.    Identify primary Deliverable
  4.    Identify Project Scope
 Discuss Question
Answer: Option C. -> Identify primary Deliverable
Answer: (c).Identify primary Deliverable
Question 28. The project team has access to whatever technical knowledge resides in the
  1.    Functional group
  2.    Marketing group
  3.    Sales group
  4.    Subcontractors group
 Discuss Question
Answer: Option A. -> Functional group
Answer: (a).Functional group
Question 29. Software projects are a common type of project organized by
  1.    Services
  2.    Products
  3.    Enterprises
  4.    Managers
 Discuss Question
Answer: Option B. -> Products
Answer: (b).Products
Question 30. A project document that describes all the work that must be done to complete the project, is known as
  1.    Work Basic Structure
  2.    Work Breakdown Structure
  3.    Work Break Structure
  4.    Work Boundary Structure
 Discuss Question
Answer: Option B. -> Work Breakdown Structure