Question 621. The integration of all the aspects of the project is done by
  1.    Group Leaders
  2.    Project Managers
  3.    Project Coordinators
  4.    Project Assembler
 Discuss Question
Answer: Option B. -> Project Managers
Answer: (b).Project Managers
Question 622. The most common pattern of progress that is implemented by the PMs in achieving the project goal is
  1.    High Progress
  2.    Slow-rapid-slow progress
  3.    Slow to high progress
  4.    High to Slow Progress
 Discuss Question
Answer: Option B. -> Slow-rapid-slow progress
Answer: (b).Slow-rapid-slow progress
Question 623. There is a tendency to think of a project solely in terms of its
  1.    Filing
  2.    Outcomes
  3.    Decision making abilities
  4.    Inputs
 Discuss Question
Answer: Option B. -> Outcomes
Answer: (b).Outcomes
Question 624. Delays in one project cause delays in other projects because of
  1.    Resource Allocation
  2.    Interdependencies
  3.    Technological Dependencies
  4.    Manager's Performance
 Discuss Question
Answer: Option C. -> Technological Dependencies
Answer: (c).Technological Dependencies
Question 625. The phase when project concept is being developed and subjected to project selection processes, requires
  1.    Maximum effort
  2.    0 effort
  3.    Minimal effort
  4.    High-peak effort
 Discuss Question
Answer: Option C. -> Minimal effort
Answer: (c).Minimal effort
Question 626. Project Management Institute (PMI), was established in
  1.    1968
  2.    1967
  3.    1969
  4.    1971
 Discuss Question
Answer: Option C. -> 1969
Answer: (c).1969
Question 627. The people in the project, the project manager, project team, senior management and the client, all are
  1.    Shareholders
  2.    Stakeholders
  3.    Team members
  4.    Project Members
 Discuss Question
Answer: Option B. -> Stakeholders
Answer: (b).Stakeholders
Question 628. The direct project objectives that are to be achieved in a project is cost, performance and
  1.    Scope
  2.    Time
  3.    Success Rate
  4.    Management methodology
 Discuss Question
Answer: Option B. -> Time
Answer: (b).Time
Question 629. The exponential growth of PMI is indicative of the rapid growth in the
  1.    Project less Organization
  2.    Project-Oriented Organizations
  3.    Design-Oriented Organization
  4.    IT Systems oriented Organizations
 Discuss Question
Answer: Option B. -> Project-Oriented Organizations
Answer: (b).Project-Oriented Organizations
Question 630. Global competition is putting more pressure on prices, response times, and product/service's
  1.    Production
  2.    Assembly
  3.    Innovation
  4.    Marketing
 Discuss Question
Answer: Option C. -> Innovation
Answer: (c).Innovation