Sail E0 Webinar
Question
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then
Options:
A .  expected time of activity A is greater than the expected time of activity B
B .  expected time of activity B is greater than the expected time of activity A
C .  expected time of both activities A and B are same
D .  none of the above
Answer: Option C

Submit Your Solution Below and Earn Points !
Next Question

Submit Solution

Your email address will not be published. Required fields are marked *

Latest Videos

Latest Test Papers