Total float for any activity is defined as the difference between
Options:
A .  Its latest finish time and earliest start time for its successor activity
B .  Its latest start time and earliest start time
C .  Its latest start time and earliest finish time
D .  Its earliest finish time and earliest start time for its successor activity
Answer: Option B