Sail E0 Webinar
Question
If the actual cost is $265000 and the flexible budget cost is $156000, then the flexible budget variance will be
Options:
A .  $409,000
B .  $109,000
C .  $209,000
D .  $309,000
Answer: Option B
Answer: (b).$109,000