An actual quantity of cost allocation base is $56000, budgeted quantity of cost allocation base is $17000, then the variable overhead efficiency variance is
Options:
A .  $39,000
B .  $49,000
C .  $59,000
D .  $73,000
Answer: Option A
Answer: (a).$39,000