For a foundation, find the elapsed time in which 90% of ultimate settlement will occur. The coefficient of consolidation is 4*10¯⁴cm²/s. The average drainage path is 50cm.
Options:
A .  56.38 days
B .  43.78 days
C .  61.34 days
D .  78.23 days
Answer: Option C
Answer: (c).61.34 days