Consider the following statements:In the bar chart planning1. Interdependence of the operations cannot be portrayed.2. Progress of work can be measured.3. Spare time of the activities can be determined.4. Schedule cannot be updated.
Options:
A .  1 and 4 are correct
B .  1, 2 and 3 are correct
C .  1, 2 and 4 are correct
D .  2, 3 and 4 are correct
Answer: Option A