Consider the following activities in a building construction:1. Concreting of roof slabs2. Brick-jelly lime concrete terracing3. Erection of form work for slab4. Construction of parapet wall in terraceThe correct sequence of these activities is
Options:
A .  3, 1, 4, 2
B .  1, 3, 2, 4
C .  3, 1, 2, 4
D .  1, 3, 4, 2
Answer: Option C