Sail E0 Webinar
Question
Consider the following features/factors:1. Projects are of the non-repetitive type2. Time required need not be known3. Time required is known precisely4. Events have been established for planning5. Emphasis is given to activities of projectPERT is preferred for planning because of
Options:
A .  1, 3 and 4
B .  1, 2 and 5
C .  1, 2 and 4
D .  3, 4 and 5
Answer: Option C