Sail E0 Webinar
Question
If the flexible budget amount is $21500 and fixed overhead flexible budget variance is $10000, then actual incurred cost will be
Options:
A .  $61,500
B .  $31,500
C .  $41,500
D .  $51,500
Answer: Option B
Answer: (b).$31,500

Was this answer helpful ?
Next Question

Submit Solution