Sail E0 Webinar
Question
A cost, consists of some fixed and some variable cost with respect to machine setup hours is termed as
Options:
A .  setup cost
B .  batch cost
C .  facility cost
D .  lump sum cost
Answer: Option A
Answer: (a).setup cost

Was this answer helpful ?
Next Question

Submit Solution