If the variable overhead flexible budget variance is $26000 and the flexible budget amount is $15000, then the actual incurred costs will be
Options:
A .  $21,000
B .  $11,000
C .  $31,000
D .  $41,000
Answer: Option D
Answer: (d).$41,000