Question 161. For initial surveys of tunnels, the following activities are involved : 1. Marking portal point with concrete pillars on the ground 2 Marking tunnel obligatory points on the topographical maps 3. Preliminary setting of the tunnel on the topographical Survey of India maps 3. Driving lines between the fixed obligatory points. The correct sequence of the activities is :
Answer: Option A. -> 3,2,4,1
Answer: Option D. -> None the above.
Answer: Option C. -> 6,7 m to 7.3 m
Answer: Option C. -> 4,9 m to 5.5 m
Question 165. For transferring the'tunnel alignment through shafts, we adopt the following steps : 1. Hanging two or more plumb lines in the shaft 2. Determining the bearing of the plumb lines i.e. plumb plane 3. Suspending a 35 kg weight by each plumb line 4. Immersing the weights of both the plumb lines in the buckets containingi,vater. The correct sequence of steps is :
Answer: Option A. -> 1 2 3 4
Answer: Option C. -> 75% of the ruling gradient
Answer: Option C. -> 0.60 m
Answer: Option D. -> All the above.
Answer: Option D. -> All the above.
Answer: Option B. -> three sections.