Question 31. A graphical technique for finding if changes and variation in metrics data are meaningful is known as_________________?
  1.    DRE (Defect Removal Efficiency)
  2.    Function points analysis
  3.    Control Chart
  4.    All of the mentioned
 Discuss Question
Answer: Option C. -> Control Chart
OTHERS OPTIONS ARE FORMULAS.
Question 32. In size oriented metrics, metrics are developed based on the _____________________?
  1.    number of Functions
  2.    number of user inputs
  3.    number of lines of code
  4.    amount of memory usage
 Discuss Question
Answer: Option C. -> number of lines of code
NO EXPLANATION IS AVAILABLE FOR THIS QUESTION!
Question 33. Which of the following is an indirect measure of product ?
  1.    Quality
  2.    Complexity
  3.    Reliability
  4.    All of the Mentioned
 Discuss Question
Answer: Option D. -> All of the Mentioned
ALL THE MENTIONED OPTIONS ARE INDIRECT MEASURES OF A PRODUCT.
Question 34. Which of the following is the task of project indicators ?
  1.    help in assessment of status of ongoing project
  2.    track potential risk
  3.    help in assessment of status of ongoing project & track potential risk
  4.    none of the mentioned
 Discuss Question
Answer: Option C. -> help in assessment of status of ongoing project & track potential risk
NO EXPLANATION IS AVAILABLE FOR THIS QUESTION!
Question 35. Defects removal efficiency (DRE)depends on ______________________?
  1.    E – errors found before software delivery
  2.    D – defects found after delivery to user
  3.    Both E and D
  4.    Varies with project
 Discuss Question
Answer: Option C. -> Both E and D
DRE = E / (E + D).
Question 36. The intent of project metrics is_____________________?
  1.    minimization of development schedule
  2.    for strategic purposes
  3.    assessing project quality on ongoing basis
  4.    minimization of development schedule and assessing project quality on ongoing basis
 Discuss Question
Answer: Option D. -> minimization of development schedule and assessing project quality on ongoing basis
A PROJECT METRIC IS A QUANTITATIVE MEASURE OF THE DEGREE TO WHICH A SYSTEM, COMPONENT OR PROCESS POSSESSES AN ATTRIBUTE.
Question 37. Which of the following is not an information domain required for determining function point in FPA ?
  1.    Number of user Input
  2.    Number of user Inquiries
  3.    Number of external Interfaces
  4.    Number of errors
 Discuss Question
Answer: Option D. -> Number of errors
FPA INCLUDES FIVE DOMAINS NAMELY INPUT, OUTPUT, INQUIRIES, INTERFACE AND LOGICAL FILES.