Sail E0 Webinar

MCQs

Total Questions : 25 | Page 2 of 3 pages
Question 11. If Invoice Correction Request is to be characterized as debit memo, what important changes do you suggest?
  1.    Document Category must be L (Debit Memo Request)
  2.    Billing Type would be a Debit Memo (L2)
  3.    Both A and B above
  4.    None of the above
 Discuss Question
Answer: Option C. -> Both A and B above




Question 12. Which of the following statements are correct?
  1.    An inclusive bonus quantity refers to a situation where free goods come in the form of extra goods that are free of charge
  2.    The sales deal number can be found in the item view of the delivery document
  3.    The promotion number can be found in the detail screen of the billing document
  4.    You can see delivery status information from the header and item level of the outbound delivery
 Discuss Question
Answer: Option B. -> The sales deal number can be found in the item view of the delivery document




Question 13. Free Goods is supported for which of the following in SAP R/3?
  1.    Third Party Order
  2.    Deliveries without reference to order
  3.    Make-to Order
  4.    None of the above
 Discuss Question
Answer: Option D. -> None of the above




Question 14. What is the T Code for "Cancel goods issue"?
  1.    VL08
  2.    VL09
  3.    VL10
  4.    VL
 Discuss Question
Answer: Option B. -> VL09




Question 15. Which of the following are true for Inter-Company Sales Processing?
  1.    Delivering Plant must be assigned to Selling Sales Organization
  2.    Internal Customer Number must be assigned to the Selling Sales Organization
  3.    Inter-company Billing Document Type must be assigned to Order Type
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above




Question 16. Backward scheduling is used?
  1.    To determine which Shipping Point is used for delivery
  2.    To determine whether delivery should be carried out or not
  3.    To determine material availability date
  4.    None of the above
 Discuss Question
Answer: Option C. -> To determine material availability date




Question 17. How is the schedule line determined?
  1.    Item category and document type
  2.    Item category group and strategy group on the material master record
  3.    Item category and MRP type on the material master record
  4.    MRP Type and shipping point
 Discuss Question
Answer: Option C. -> Item category and MRP type on the material master record




Question 18. Which of the following are correct for a third party order?
  1.    If a PO is not created, then Sales Order quantity may be changed which is automatically copied to Purchase Requisition (if permitted by release status)
  2.    Quantity Changes made to the PO are automatically copied to Sales Order
  3.    Both A and B are correct
  4.    None of the above
 Discuss Question
Answer: Option C. -> Both A and B are correct




Question 19. In a Business requirement the price of a material is based on the 'Region', 'Sales Org.', 'Distribution Channel' . If you were to create a Condition Table for this scenario, the order in which the fields are arranged is?
  1.    Material, Sales Organization, Distribution Channel, Region
  2.    Material, Distribution Channel, Region, Sales Organization
  3.    Sales Organization, Distribution Channel, Region, Material
  4.    None of the above
 Discuss Question
Answer: Option C. -> Sales Organization, Distribution Channel, Region, Material




Question 20. If a material is created for Plant X, how is the same material defined for Plant Y? What is the process called?
  1.    MM02 and Extending the material
  2.    MM01 and Extending the material
  3.    MM01 and Creating the material
  4.    None of the above
 Discuss Question
Answer: Option B. -> MM01 and Extending the material




Latest Videos

Latest Test Papers