Sail E0 Webinar

MCQs

Total Questions : 25 | Page 2 of 3 pages
Question 11. When scheduling a routing in the SAP ECC system, which of the following time elements is a interoperation time?
  1.    Safety time
  2.    Float before production
  3.    Processing time
  4.    Setup time
 Discuss Question
Answer: Option B. -> Float before production




Question 12. As a production manager, how do you enable process operations parallel to and independent of other operations?
  1.    Parallel sequences
  2.    Successor relationships
  3.    Control sequences
  4.    Linked sequences
 Discuss Question
Answer: Option A. -> Parallel sequences




Question 13. Consider a product scenario where there is high product stability, high repetition rates, and low product complexity. What type of manufacturing do you suggest?
  1.    Mass manufacturing
  2.    Bulk manufacturing
  3.    Repetitive manufacturing
  4.    Order based manufacturing
 Discuss Question
Answer: Option C. -> Repetitive manufacturing




Question 14. Consumption-based planning is usually used for following materials
  1.    All A & B Class Materials
  2.    Materials with smooth consumption pattern
  3.    Both a and b
  4.    None
 Discuss Question
Answer: Option B. -> Materials with smooth consumption pattern




Question 15. What is the use of BOM?
  1.    MRP
  2.    Costing
  3.    Inspection data
  4.    Sales and Distribution
  5.    All of the above
 Discuss Question
Answer: Option E. -> All of the above




Question 16. List out the activities carried out in Production Planning?
  1.    Processing material master
  2.    Creation of Bill of Material
  3.    Displaying work center and routing
  4.    All of the above
 Discuss Question
Answer: Option D. -> All of the above




Question 17. What is the T Code for changing planned order?
  1.    MD11
  2.    MD12
  3.    MD13
  4.    MD14
 Discuss Question
Answer: Option B. -> MD12




Question 18. Which SAP NetWeaver component realizes cross-system application processes?
  1.    SAP Business Warehouse (SAP BW)
  2.    SAP Enterprise Portal (SAP EP)
  3.    SAP Master Data Management (SAP MDM)
  4.    SAP Exchange Infrastructure (SAP XI) / SAP Process Integration (SAP PI)
 Discuss Question
Answer: Option D. -> SAP Exchange Infrastructure (SAP XI) / SAP Process Integration (SAP PI)




Question 19. Movement type for goods receipt into warehouse
  1.    122
  2.    123
  3.    101
  4.    102
 Discuss Question
Answer: Option C. -> 101




Question 20. The Individual / Collective indicator in the material Master determines
  1.    Whether a component is procured for a special customer requirement in the individual segment
  2.    Requirement quantities of dependent materials are grouped together during MRP run
  3.    The Material Requirement Planning
  4.    The Special Procurement
 Discuss Question
Answer: Option C. -> The Material Requirement Planning