Total Questions : 25 | Page 3 of 3 pages
Question 21. How do you generate short orders without a task list if no task has been entered in the maintenance item for the maintenance plan?
  1.    The system copies the short text for the maintenance plan into the maintenance order as an operation description
  2.    The task list has to be entered compulsorily
  3.    Task list is generated but the planner cannot add additional operations to the maintenance order
  4.    This leads to errors in scheduling data
 Discuss Question
Answer: Option A. -> The system copies the short text for the maintenance plan into the maintenance order as an operation description




Question 22. How do you cover some objects that are maintained in a fixed cycle determined by a standard?
  1.    Object maintenance planning
  2.    Fixed cycle maintenance planning
  3.    Single cycle maintenance planning
  4.    Scheduled maintenance planning
 Discuss Question
Answer: Option C. -> Single cycle maintenance planning




Question 23. Which of the following determines the maintenance package will be performed if two maintenance packages are due at the same time?
  1.    Cycle Length
  2.    Offset
  3.    Hierarchy
  4.    Initial Buffer
 Discuss Question
Answer: Option C. -> Hierarchy




Question 24. Which of the following T-code is used to create a Warranty object?
  1.    IE01
  2.    IL01
  3.    IQ01
  4.    IB51
 Discuss Question
Answer: Option A. -> IE01




Question 25. Which data is useful to monitor a piece of equipment dynamically that is track changes to the equipment over a specific period of time?
  1.    Period-based data
  2.    Equipment data
  3.    Time segment
  4.    Time-based data
 Discuss Question
Answer: Option D. -> Time-based data