Question 281. In the halsey system of wage incentive plan, a worker is
  1.     Paid as per efficiency
  2.     Ensured of minimum wages
  3.     Not paid any bonus till his efficiency
  4.     Never a loser
 Discuss Question
Answer: Option B. ->  Ensured of minimum wages
Explanation :
Question 282. Pert is the
  1.     Time oriented technique
  2.     Event oriented technique
  3.     Activity oriented technique
  4.     Target oriented technique
 Discuss Question
Answer: Option B. ->  Event oriented technique
Explanation :
Question 283. If ‘f’ is the fixed cost, ‘v’ is the variable cost per unit (or total variable costs) and ‘p’ is the selling price of each unit (or total sales value), then break-even point is equal to
  1.     (F × V)/P
  2.     (F × P)/V
  3.     F/[1 + (V/P)]
  4.     F/[1 - (V/P)]
 Discuss Question
Answer: Option D. ->  F/[1 - (V/P)]
Explanation :
Question 284. If ‘f’ is the fixed cost, ‘v’ is the variable cost per unit (or total variable costs) and ‘p’ is the selling price of each unit (or total sales value), then break-even point is equal to
  1.     (F × V)/P
  2.     (F × P)/V
  3.     F/[1 + (V/P)]
  4.     F/[1 - (V/P)]
 Discuss Question
Answer: Option D. ->  F/[1 - (V/P)]
Explanation :
Question 285. If ‘f’ is the fixed cost, ‘v’ is the variable cost per unit (or total variable costs) and ‘p’ is the selling price of each unit (or total sales value), then break-even point is equal to
  1.     (F × V)/P
  2.     (F × P)/V
  3.     F/[1 + (V/P)]
  4.     F/[1 - (V/P)]
 Discuss Question
Answer: Option D. ->  F/[1 - (V/P)]
Explanation :
Question 286. Job enrichment technique is applied to
  1.     Reduce labour monotony
  2.     Overcome boring and demotivating work
  3.     Make people happy
  4.     All of the above
 Discuss Question
Answer: Option D. ->  All of the above
Explanation :
Question 287. Slack represents the difference between the
  1.     Latest allowable time and the normal expected time
  2.     Latest allowable time and the earliest expected time
  3.     Proposed allowable time and the earliest expected time
  4.     Normal allowable time and the latest expected time
 Discuss Question
Answer: Option B. ->  Latest allowable time and the earliest expected time
Explanation :
Question 288. Pick up the correct statement from the following
  1.     If the float is positive and the activity is delayed by a period equal to its total float, the completion of project in not delayed
  2.     If the float of an activity is negative, delay in its performance is bound to delay the completion of project
  3.     If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
  4.     All of the above
 Discuss Question
Answer: Option D. ->  All of the above
Explanation :
Question 289. Discrepancies of bar chart techniques are
  1.     Consequential effects of lack in one activity on the finish date
  2.     Free time available for an activity can't be predicted
  3.     Effective monitoring/controlling can't be done
  4.     All of the above
 Discuss Question
Answer: Option D. ->  All of the above
Explanation :
Question 290. Pick up the incorrect statement from the following
  1.     An activity of the project is denoted by an arrow on the net work
  2.     The tail of the arrow indicates the start of the activity
  3.     The head of the arrow indicates the end of the activity
  4.     The arrows are drawn (to scale from) left to right
 Discuss Question
Answer: Option D. ->  The arrows are drawn (to scale from) left to right
Explanation :