Pick up the incorrect statement from the following
Options:
A .   An activity of the project is denoted by an arrow on the net work
B .   The tail of the arrow indicates the start of the activity
C .   The head of the arrow indicates the end of the activity
D .   The arrows are drawn (to scale from) left to right
Answer: Option D
Explanation :