Question 301. 5. Portion of the installed reserve kept in operable condition but not placed in service to supply the peak load is known as
  1.    Operating reserve
  2.    Spinning reserve
  3.    Cold reserve
  4.    Hot reserve
 Discuss Question
Answer: Option C. -> Cold reserve
Question 302. 1. The ratio of maximum load to rated plant capacity is known as
  1.    Load factor
  2.    Utilization factor
  3.    Maximum load factor
  4.    Capacity factor
 Discuss Question
Answer: Option B. -> Utilization factor
Question 303. 3. Capacity of a hydroelectric plant in service in excess of the peak load is known as
  1.    Operating reserve
  2.    Spinning reserve
  3.    Cold reserve
  4.    Hot reserve
 Discuss Question
Answer: Option A. -> Operating reserve
Question 304. 2. Portion of the installed reserve kept in operable condition but not placed in service to supply the peak load is known as
  1.    Operating reserve
  2.    Spinning reserve
  3.    Cold reserve
  4.    Hot reserve
 Discuss Question
Answer: Option C. -> Cold reserve