MCQs
Total Questions : 195
| Page 10 of 20 pages
Answer: Option A. -> activity based costing
Answer: (a).activity based costing
Answer: (a).activity based costing
Answer: Option C. -> variable setup costs
Answer: (c).variable setup costs
Answer: (c).variable setup costs
Answer: Option B. -> $112,500
Answer: (b).$112,500
Answer: (b).$112,500
Answer: Option A. -> $10,000
Answer: (a).$10,000
Answer: (a).$10,000
Answer: Option D. -> production volume variance
Answer: (d).production volume variance
Answer: (d).production volume variance
Answer: Option C. -> non-financial measures
Answer: (c).non-financial measures
Answer: (c).non-financial measures
Answer: Option B. -> fixed setup costs
Answer: (b).fixed setup costs
Answer: (b).fixed setup costs
Answer: Option C. -> $47,000
Answer: (c).$47,000
Answer: (c).$47,000
Answer: Option B. -> compute the per unit rate
Answer: (b).compute the per unit rate
Answer: (b).compute the per unit rate
Answer: Option A. -> $20,000
Answer: (a).$20,000
Answer: (a).$20,000