MCQs
Total Questions : 153
| Page 12 of 16 pages
Answer: Option A. -> checks the seepage
Answer: (a).checks the seepage
Answer: (a).checks the seepage
Answer: Option B. -> 2.5: 1
Answer: (b).2.5: 1
Answer: (b).2.5: 1
Answer: Option C. -> 3 m above the top of gates
Answer: (c).3 m above the top of gates
Answer: (c).3 m above the top of gates
Answer: Option A. -> Zoned embankment type
Answer: (a).Zoned embankment type
Answer: (a).Zoned embankment type
Answer: Option B. -> 0.2H + 3
Answer: (b).0.2H + 3
Answer: (b).0.2H + 3
Answer: Option A. -> R = Rₑ (W/B)^0.61
Answer: (a).R = Rₑ (W/B)^0.61
Answer: (a).R = Rₑ (W/B)^0.61
Answer: Option B. -> regime width
Answer: (b).regime width
Answer: (b).regime width
Question 118. A road bridge is proposed to be constructed across an alluvial stream with the estimated design discharge as 2500 m³/s. It is decided to adopt a total effective waterway equal to 300 m for this bridge as against the regime width of 237.5 m due to afflux considerations. If the HFL at the site is at RL 214 m, then the RL of the open foundation can be suggested as _______
Answer: Option A. -> 206.6 m
Answer: (a).206.6 m
Answer: (a).206.6 m
Answer: Option B. -> 7.5 m
Answer: (b).7.5 m
Answer: (b).7.5 m
Answer: Option B. -> 8 m
Answer: (b).8 m
Answer: (b).8 m